RUSCHEM Group is evaluating options for establishing a new vertically integrated gas chemical complex in the Arctic Zone. The project is implemented within the framework of the Strategy for Development of the Arctic Zone and Ensuring National Security of the Russian Federation 2035.

The estimated investments in establishing the new facility and infrastructure exceed 200 bln. rubles. The project will create new jobs both at the construction stage and upon the complex operation.

The gas condensate resource hubs are planned on the basis of Kumzhinsky and Korovinsky gas-condensate fields in the Nenets Autonomous Area. Also, RUSCHEM is considering construction of a methanol plant with associated export-oriented seaport infrastructure.
ABOUT
THE PROJECT
ABOUT THE PROJECT
RUSCHEM Group is evaluating options for establishing a new vertically integrated gas chemical complex in the Arctic Zone. The project is implemented within the framework of the Strategy for Development of the Arctic Zone and Ensuring National Security of the Russian Federation 2035.

The estimated investments in establishing the new facility and infrastructure exceed 200 mln. rubles. The project will create new jobs both at the construction stage and upon the complex operation.

The gas condensate resource hubs are planned on the basis of Kumzhinsky and Korovinsky gas-condensate fields in the Nenets Autonomous Area. Also, RUSCHEM is considering construction of a methanol plant with associated export-oriented seaport infrastructure.
GAS CHEMICAL
COMPLEX
LOCATION
THE ROUTE OF DELIVERY OF COMMERCIAL METHANOL
GAS CHEMICAL
COMPLEX
MODEL
STAGES
OF THE PROJECT
REALISATION
STAGES
OF THE PROJECT
REALISATION
I stage: methanol production
2020-2028
Design and Implementation
  • methanol plant (1.8 mln. tpa);
  • development of Kumzhinsky field for 2 bln. m3 per year;
  • gas preparing infrastructure and marine shipment terminal.
2029
Launch of the I project stage
  • commencement of the methanol plant operation based on Kumzhinsky gas-condensate field.
II stage: complex expantion
2025-2030
Construction of the II project stage
  • complex expansion: additional production line;
  • increase at Kumzhinsky field to 4 bln. m3 per year;
  • expansion of gas preparing infrastructure.
2031
Launch of the II project stage
  • methanol plant operation based on Kumzhinsky gas-condensate field;
  • stable production to 4 bln. m3 per year including Korovinsky gas-condensate field development.
I stage: methanol production
2020-2028
Design and Implementation
  • methanol plant (1.8 mln. tpa);
  • development of Kumzhinsky field for 2 bln. m3 per year;
  • gas preparing infrastructure and marine shipment terminal.
2029
Launch of the I project stage
  • commencement of the methanol plant operation based on Kumzhinsky gas-condensate field.
II stage: complex expantion
2025-2030
Construction of the II project stage
  • complex expansion: additional production line;
  • increase at Kumzhinsky field to 4 bln. m3 per year;
  • expansion of gas preparing infrastructure.
2031
Launch of the II project stage
  • methanol plant operation based on Kumzhinsky gas-condensate field;
  • stable production to 4 bln. m3 per year including Korovinsky gas-condensate field development.
CONTACTS
info@ruschem.group
MOSCOW
10, Testovskaya St.,
Floor 15, Room 1,
Moscow, Russia, 123112
MOSCOW
30A, Bolshaya Gruzinskaya St.,
Bldg. 1, Office 609,
Moscow, Russia, 123056
SAINT PETERSBURG
80, Bolshoi Prospekt V.O.,
Bldg. “P”, Saint Petersburg, 199106
NARYAN-MAR
131, V.I. Lenin St., Room 26,
Naryan-Mar, the Nenets Autonomous Area, 166000
info@ruschem.group
Made on
Tilda