GAS CHEMICAL
COMPLEX
IN THE ARCTIC
ZONE
CH3OH
METHANOL
PRODUCTION
COMPLEX
START
OF THE PROJECT
2025
GAS CHEMICAL
COMPLEX
IN THE ARCTIC
ZONE
RUSHIM Group is evaluating options for establishing a new vertically integrated gas chemical complex in the Arctic Zone. The project is implemented within the framework of the Strategy for Development of the Arctic Zone and Ensuring National Security of the Russian Federation 2035.

The estimated investments in establishing the new facility and infrastructure exceed 200 mln. rubles. The project will create new jobs both at the construction stage and upon the complex operation.

The gas condensate resource hubs are planned on the basis of Kumzhinsky and Korovinsky gas-condensate fields in the Nenets Autonomous Area. Also, RUSHIM is considering construction of a methanol plant based on Air Liquide technology with associated export-oriented seaport infrastructure.
ABOUT
THE PROJECT
ABOUT THE PROJECT
RUSHIM Group is evaluating options for establishing a new vertically integrated gas chemical complex in the Arctic Zone. The project is implemented within the framework of the Strategy for Development of the Arctic Zone and Ensuring National Security of the Russian Federation 2035.

The estimated investments in establishing the new facility and infrastructure exceed 200 mln. rubles. The project will create new jobs both at the construction stage and upon the complex operation.

The gas condensate resource hubs are planned on the basis of Kumzhinsky and Korovinsky gas-condensate fields in the Nenets Autonomous Area. Also, RUSHIM is considering construction of a methanol plant based on Air Liquide technology with associated export-oriented seaport infrastructure.
GAS CHEMICAL
COMPLEX
LOCATION
THE ROUTE OF DELIVERY OF COMMERCIAL METHANOL
GAS CHEMICAL
COMPLEX
MODEL
STAGES
OF THE PROJECT
REALISATION
STAGES
OF THE PROJECT
REALISATION
01
02
03
2020/ 2025
2025/ 2027
2026/ 2027
Design and Implementation Stage: development of Kumzhinsky field for 2 bln. m3 per year, methanol plant design and construction for 1.8 mln tpa methanol and marine shipment terminal in the settlement of Krasnoye.
Commencement of the methanol plant operation.
Complex Expansion: production increase at Kumzhinsky field to 4 bln. m3 per year, methanol plant capacity increase to 3.6 mln. tpa methanol.
01
2020/ 2025
Design and Implementation Stage: development of Kumzhinsky field for 2 bln. m3 per year, methanol plant design and construction for 1.8 mln tpa methanol and marine shipment terminal in the settlement of Krasnoye.
02
2025/ 2027
Commencement of the methanol plant operation.
03
2026/ 2027
Complex Expansion: production increase at Kumzhinsky field to 4 bln. m3 per year, methanol plant capacity increase to 3.6 mln. tpa methanol.
CONTACTS
info@ruschem.group
MOSCOW
10, Testovskaya St.,
Floor 15, Room 1,
Moscow, Russia, 123112
MOSCOW
30A, Bolshaya Gruzinskaya St.,
Bldg. 1, Office 609,
Moscow, Russia, 123056
SAINT PETERSBURG
80, Bolshoi Prospekt V.O.,
Bldg. “P”, Saint Petersburg, 199106
NARYAN-MAR
131, V.I. Lenin St., Room 26,
Naryan-Mar, the Nenets Autonomous Area, 166000
VK
OK
TG
VK
OK
TG
info@ruschem.group
Made on
Tilda